§ 14-2. Acceptance of improvements.


Latest version.
  • (a)

    Upon the satisfactory completion of construction, the subdivider shall obtain written final approval and acceptance from the designated engineering review agency and submit this approval to the planning commission.

    (b)

    For a period of 12 months after acceptance of the work the subdivider shall keep all filled trenches, pipes, manholes, structures, paving, etc., constructed by him in good condition, making repairs to such defects in material or workmanship as may develop or be discovered. The subdivider shall file with the commission, a surety bond, securing to the City of Rayne the satisfactory performance of this work for a period of one year from the date of such bond. The amount of the bond shall be ten percent of the cost of the improvements as determined by the designated engineering review agency. The form of the bond shall be approved by the City of Rayne's legal council. The bond shall be subject to cancellation only upon written approval of the designated engineering review agency.